dc.contributor.author | Sahid, Muh Nur | |
dc.contributor.author | Priyanto, Budi | |
dc.contributor.author | Anggoro, Danu Tri | |
dc.date.accessioned | 2015-02-04T02:43:35Z | |
dc.date.available | 2015-02-04T02:43:35Z | |
dc.date.issued | 2014-09 | |
dc.identifier.citation | Badri, S., 2001. Dasar-Dasar Network Planning. Jakarta: Rineka Cipta. Djojowirono, S., 2005. Manajemen Konstruksi. Edisi Keempat. Jakarta: Erlangga. Metode Jalur Kritis (CPM) :http://www.mdp.ac.id/materi/2011-2012-1/MJ203/012018/MJ203-012018- 670-3.doc Munandar, M., 1996. Materi Pokok Manajemen Proyek. Jakarta: Karunika. Soeharto, I., 1999. Manajemen Konstruksi Dari Konseptual Hingga Operasional. Jakarta: Erlangga. Soetrisno, 1985. Dasar-Dasar Evaluasi dan Manajemen Proyek, Yogyakarta: Universitas Gajah Mada. | en_US |
dc.identifier.issn | 1907-4026 | |
dc.identifier.uri | http://hdl.handle.net/11617/5188 | |
dc.description.abstract | A solution that can be implemented if it has been a delay is done accelerating the implementation of
the additional hours worked. To perform the analysis of additional hours worked by the costs incurred
can be carried out by the method of Time Cost Trade Off Analysis .. The point is to accelerate
project implementation time of analyzing the extent to which time can be shortened by increasing
the costs of the activities that can be accelerated execution time. Projects are chosen the library and
archives building Batang district because of the demand on the part of the contractor to accelerate
project completion time of a plan that is already listed in the contract due to the delay in the work.
With limited resources, the acceleration of the project is carried out by working overtime for 3 hours
a day. Crashing the work done on the items contained in the critical path of the job starts with the
smallest cost slope. Compression is performed directly to lead to increased costs and reduced indirect
costs. From the calculation, the critical time for 52 days (<9 weeks), or 10 days earlier than the
normal time is 62 days, an increase in Rp6.746.451,21 from fixed costs Rp91.259.054,91 to
Rp98.005.506,12. Then the variable cost for 24 days of overtime for a total of Rp11.023.213,87. So
we get the total job costs Rp109.028.713,87. | en_US |
dc.publisher | Universitas Muhammadiyah Surakarta | en_US |
dc.subject | Time Cost Trade Off Analysis | en_US |
dc.subject | overtime hour | en_US |
dc.subject | cost | en_US |
dc.title | The Effect of Overtime Hour to Charge with Time Cost Trade Off Analysis | en_US |
dc.type | Article | en_US |