Evaluation of Factors Causing the Construction Project Delay: Case Study of PT Jagat Konstruksi's Projects, 2016- 2019
View/ Open
Date
2020-12Author
Fajerin, Yan Anggitia
Solikin, Mochamad
Qomarun, Qomarun
Metadata
Show full item recordAbstract
Construction projects generally have a planned and scheduled time. However, in the
reality there are still obstacles in project work delays, such as in PT Jagat Konstruksi, Jakarta.
This article will discuss about project delays. The purpose of this study is to find the main
causes of project delays and to identify and classify the causes of the delay. The research was
conducted by a case study method on 5 projects handled by PT Jagat Konstruksi during 2016-
2019. To analyze the delay (Mean, Average, Relative Index, Factor Analysis), it is done with
statistical tools, such as Excel and SPSS. The delay in the construction project was caused by a
chain reaction, from one factor to another. This research finds that the shortage of labour aspect
is the strongest factor. Meanwhile, the research results show that there are 4 groups project
delay factors: (1) resources availability; (2) internal limitation; (3) external limitation; and (4)
financial.