MODIFIKASI MEKANISME PENENTUAN PENJADWALAN JOB PADA METODE DANNENBRING
Abstract
Scheduling methods particularly in scheduling a job toward machine
capacity is often not optimal in generating the minimum makespan time due to
the inappropriate mechanism of determining the schedule from the job. By using
an appropriate mechanism on the local search for both of the job order towards
machine and the recapitulation of the makespan in each job in order to produce
the optimal scheduling is proved an effective approach to minimize the error of
the end time processes that are too long. This approach is also able to provide the
optimal solution for the work planning. This research focuses on the searching
for some mechanism design alternatives in job scheduling by employing the
makespan recapitulation table of each job on the machine determined by
Dannenbring method. The result of this research shows that the smallest possible
makespan time is 93, by following the order of job j1-j7-j2-j8-j4-j5-j6-j3, j1-j6j2-j7-j8-j4-j5-j3
and j1-j6-j2-j4-j8-j7-j5-j3 using hybrid Pi1 earlier mechanism
and hybrid Pi2 earlier mechanism.